Jara, K., (2024). Aplicación del Lean Construction en la obra "Construcción de la recepción del centro recreacional del Ilustre Colegio de Abogados" ejecutado por la empresa "Onix Building Company" en el distrito de Oropesa, provincia de Cusco - 2019. [Universidad Andina del Cusco]. https://hdl.handle.net/20.500.12557/7011
Jara, K., Aplicación del Lean Construction en la obra "Construcción de la recepción del centro recreacional del Ilustre Colegio de Abogados" ejecutado por la empresa "Onix Building Company" en el distrito de Oropesa, provincia de Cusco - 2019. []. PE: Universidad Andina del Cusco; 2024. https://hdl.handle.net/20.500.12557/7011
@misc{renati/999325,
title = "Aplicación del Lean Construction en la obra "Construcción de la recepción del centro recreacional del Ilustre Colegio de Abogados" ejecutado por la empresa "Onix Building Company" en el distrito de Oropesa, provincia de Cusco - 2019.",
author = "Jara Ninalaya, Katherine Mia",
publisher = "Universidad Andina del Cusco",
year = "2024"
}
The purpose of this research was the implementation of 03 Lean Construction tools in the work “Construcción de la Recepción del Centro Recreacional del Ilustre Colegio de Abogados", to leave a positive precedent in the company Onix Building Company, since being part of the implementation of these tools and have a database with all the information on the implementation of the Lasta Planner System, Balance Letters and 5-minute Test in the project "Construction of the Reception of the Recreational Center of the Illustrious Bar Association", will be able carry out the application of these tools in the next works that will be executed on your part. For the development of this research, the company Onix Building Company was willing to implement this philosophy from the beginning of the planning of the project: “Construcción de la Recepción del Centro Recreacional del Ilustre Colegio de Abogados", where the Last Planner System tool was applied . to obtain the Percentage of Complete PPC Plan, throughout the execution of the project, likewise the Balance Cards tool was applied that allowed us to obtain the labor performance, finally the 5-minute test tool was applied, to analyze the use of a worker's time. The main objective of this research was: How the application of Lean Construction influences the productivity that took place in the implementation of the work “Construction of the reception of the recreational center of the Illustrious College of Lawyers” to obtain the stated objectives. Data was collected in the field by applying the Balance Charts tool, data that was collected in the most relevant items in each week, and taking a continuous minute by minute recording.