Buscar en Google Scholar
Título: Implementación de la curva de liberación en el last planner system para controlar el impacto del síndrome del 90 % en proyectos multifamiliares
Otros títulos: Implementation of the release curve in the last planner® system to control the impact of the 90% syndrome in multi-family projects
Campo OCDE: https://purl.org/pe-repo/ocde/ford#2.01.03
Fecha de publicación: 27-sep-2021
Institución: Universidad Peruana de Ciencias Aplicadas (UPC)
Resumen: Las empresas constructoras del sector inmobiliario, conforme se acercan a la fecha de entrega del proyecto, enfrentan mayor dificultad para culminarlo. Esto, por lo general, sucede cuando la obra se encuentra alrededor de un 90 % de avance, y el 10 % de avance restante no se comporta de la misma manera que lo ya realizado, generándose ampliaciones de plazo. Cuando se produce esta condición, decimos que se ha generado el Síndrome del 90 %. La gran mayoría de las empresas constructoras del sector inmobiliario plantean su programación de obra en base a la Curva S, o Curva de Avance, y descuidan el control de lo que se viene liberando en la obra. Este comportamiento es el principal motivo por el cual se genera el Síndrome del 90 %, razón por la cual se realiza el presente trabajo de investigación, para diseñar una metodología que reconozca, mitigue y revierta los efectos negativos que este síndrome pueda producir. La propuesta ha sido aplicada a un proyecto multifamiliar en curso y plantea generar una curva adicional a la tradicional Curva S haciendo uso del Last Planner® System. Se trata de la Curva de Liberación, la cual recogerá la data de cómo se están produciendo las liberaciones de partidas de nuestra obra, otorgándonos información que nos permita elaborar una programación que nos aleje del Síndrome del 90 % y de los efectos negativos que éste produce, tales como la ampliación de plazos, el incremento en los costos, las penalidades por no cumplimiento y una segura afectación a la imagen comercial de la empresa.

As the building companies in the real estate sector approach the project delivery date, they face greater difficulty finishing it. This, in general, happens when the work is around 90% complete, and the remaining 10% progress does not behave in the same way as what has already been done, generating an increase in the schedule. When this condition occurs, we say that the 90% Syndrome has been generated. The vast majority of building companies in the real estate sector plan their work schedule based on the S Curve, or progress curve, and neglect to control what is being released in the work. This behavior is the main reason why the 90% Syndrome is generated, which is why this research work is carried out, to design a methodology that recognizes, mitigates and reverses the negative effects that this syndrome may produce. The proposal has been applied to an ongoing multifamily building and proposes generating an additional curve to the traditional S Curve using the Last Planner® System. This is the release curve, which will collect the data on how the releases of items of our work are taking place, providing us with information that allows us to develop a schedule that moves us away from the 90% Syndrome and the negative effects it produces, such as the schedule increase, the cost increase, penalties for non-completion and a certain impact on the commercial image of the company.
Enlace al repositorio: http://hdl.handle.net/10757/658482
Disciplina académico-profesional: Maestría en Dirección de la Construcción
Institución que otorga el grado o título: Universidad Peruana de Ciencias Aplicadas (UPC). Escuela de Postgrado
Grado o título: Maestro en Dirección de la Construcción
Fecha de registro: 6-ene-2022



Este ítem está sujeto a una licencia Creative Commons Licencia Creative Commons Creative Commons