Citas bibligráficas
Esta es una referencia generada automáticamente. Modifíquela de ser necesario
Donet, L., (2020). Hincado de pilotes y dragado en el muelle norte del puerto del Callao [Trabajo de suficiencia profesional, Universidad Nacional de Ingeniería]. http://hdl.handle.net/20.500.14076/21683
Donet, L., Hincado de pilotes y dragado en el muelle norte del puerto del Callao [Trabajo de suficiencia profesional]. PE: Universidad Nacional de Ingeniería; 2020. http://hdl.handle.net/20.500.14076/21683
@misc{renati/711305,
title = "Hincado de pilotes y dragado en el muelle norte del puerto del Callao",
author = "Donet Sanchez, Luis Antonio",
publisher = "Universidad Nacional de Ingeniería",
year = "2020"
}
Título: Hincado de pilotes y dragado en el muelle norte del puerto del Callao
Autor(es): Donet Sanchez, Luis Antonio
Asesor(es): Fuentes Ortíz, César Alfredo
Palabras clave: Ampliación de puerto; Hincado de pilotes; Dragado; Prefabricados
Campo OCDE: http://purl.org/pe-repo/ocde/ford#2.01.01
Fecha de publicación: 2020
Institución: Universidad Nacional de Ingeniería
Resumen: El presente trabajo de suficiencia profesional desarrolla los procesos constructivos de mayor influencia en el proyecto “Ampliación del Terminal Multipropósito Muelle Norte – Callao”, obra que busca incrementar su capacidad, al doble, para poder atender la creciente cantidad de importaciones y exportaciones que se vienen dando en lo que respecta al comercio exterior del país.
En primer lugar, se empieza detallando los conceptos generales asociados a los puertos y su infraestructura, así como procedimientos constructivos a tomar en cuenta.
Luego se centra en las actividades concretas realizadas en el proyecto mencionado, los cuales comienzan con la demolición de la plataforma existente, así como también se procede al retiro de los pilotes que sujetan dicho parte demolida, posteriormente se continua con el proceso de dragado y conformación de la nueva sección transversal del puerto (aumento de calado), teniendo luego lo colocación de los pilotes nuevos que sostendrán la ampliación de la plataforma. Principalmente los procesos anteriormente mencionados serán aquellos que se detallarán en los posteriores capítulos.
De los procedimientos mencionados se tiene la recopilación de problemas presentados durante la ejecución, así como las medidas tomadas para su solución y lecciones aprendidas.
Asimismo, se detalla la incidencia económica de los problemas presentados dentro del monto de la obra.
This research develops the main construction procedures for the Expansion Project of El Callao Multipurpose Northern Terminal, work that seeks to increase its capacity, to double, in order to be able to attend the growing quantity of imports and exports that are taking place in regards to foreign trade of the country. In first place, it is started detailing all general concepts linked to ports and their infrastructure, as well as the construction procedures to take into account. After, it is focused on the main activities made in the mentioned project, which begin with demolition of part of the existing platform, as well as the removal of the piles that hold the demolished part, and then dredging process continues and the new cross section of the port is formed (draft increase); then having the placement of the new piles that will support the expansion of the platform. Mainly the processes mentioned formerly will be those that develop next chapters. These processes include the compilation of problems presented during the execution, as well as the measures taken to solve them and the lessons learned. Likewise, the economic incidence of the problems presented within the amount of the work is
This research develops the main construction procedures for the Expansion Project of El Callao Multipurpose Northern Terminal, work that seeks to increase its capacity, to double, in order to be able to attend the growing quantity of imports and exports that are taking place in regards to foreign trade of the country. In first place, it is started detailing all general concepts linked to ports and their infrastructure, as well as the construction procedures to take into account. After, it is focused on the main activities made in the mentioned project, which begin with demolition of part of the existing platform, as well as the removal of the piles that hold the demolished part, and then dredging process continues and the new cross section of the port is formed (draft increase); then having the placement of the new piles that will support the expansion of the platform. Mainly the processes mentioned formerly will be those that develop next chapters. These processes include the compilation of problems presented during the execution, as well as the measures taken to solve them and the lessons learned. Likewise, the economic incidence of the problems presented within the amount of the work is
Enlace al repositorio: http://hdl.handle.net/20.500.14076/21683
Disciplina académico-profesional: Ingeniería Civil
Institución que otorga el grado o título: Universidad Nacional de Ingeniería. Facultad de Ingeniería Civil
Grado o título: Ingeniero Civil
Jurado: Atala Abad, César Augusto; Colonio García, Luis Alfredo
Fecha de registro: 8-feb-2022
Este ítem está sujeto a una licencia Creative Commons Licencia Creative Commons