Julca, P., (2022). Análisis de rendimiento de mano de obra en creación del servicio de protección contra inundaciones de la margen derecha del río Huallaga km 0+000 al 2+122 en la localidad de Pilluana, provincia de Picota, departamento de San Martín [Tesis, Universidad Cientìfica del Perù]. http://hdl.handle.net/20.500.14503/2283
Julca, P., Análisis de rendimiento de mano de obra en creación del servicio de protección contra inundaciones de la margen derecha del río Huallaga km 0+000 al 2+122 en la localidad de Pilluana, provincia de Picota, departamento de San Martín [Tesis]. PE: Universidad Cientìfica del Perù; 2022. http://hdl.handle.net/20.500.14503/2283
@misc{renati/195524,
title = "Análisis de rendimiento de mano de obra en creación del servicio de protección contra inundaciones de la margen derecha del río Huallaga km 0+000 al 2+122 en la localidad de Pilluana, provincia de Picota, departamento de San Martín",
author = "Julca Rimarachin, Pamela Isabel",
publisher = "Universidad Cientìfica del Perù",
year = "2022"
}
In the investigation, the objective is to determine the yields of the workforce, for which the performance of the workforce was controlled during the process, based on what is described in the technical file, and then compared with the real executed in the stone extraction and selection activities and the filling of a 5 x 2 x 0.3 m gabion. The elaboration of tables for the collection of data in the field and processing them in the office, comparing the yields of labor in the Works obtained on site with the Yields of the Unit Cost Analysis of the Technical File. Following the methodology established by CAPECO, indicated by Ramos Salazar, Jesús (2004), considering the man-hours consumed, the daily performance stipulated in the technical file and following the protocols, in order to execute the daily performance, it was possible to obtain what was actually executed. The results in the execution of the activity of extraction and selection of stone, no difficulties were generated during the execution of the work, being the real meters executed coincident with those programmed in the technical file; but regarding the assembly, installation and placement of 5 * 2 * 0.3m gabion, the labor consumption was 64h, programmed and 194h executed. In conclusion, in all types of work, the contractor that executes said work is to carry it out in the contracted time, in order for said goal to be met, the yields on the work must be fulfilled according to the yields established in the unit cost analysis of the contracted technical file.