Look-up in Google Scholar
Title: Optimización de costos en obra mediante la reducción de plazos de desencofrado al aumentar resistencia inicial de concreto, Ica, 2022
Advisor(s): Neyra Torres, Jose Luis
OCDE field: https://purl.org/pe-repo/ocde/ford#2.01.01
Issue Date: 19-Jul-2023
Institution: Universidad Privada del Norte
Abstract: La presente investigación busca optimizar los costos en obra mediante la reducción de plazos de desencofrado al aumentar resistencia inicial del concreto de 175kg/cm2 a 210 kg/cm2 y 245kg/cm2, en los costos de desencofrado de elementos horizontales (losas macizas) en una obra realizada durante dos etapas en la ciudad de Ica durante el año 2022, de las que el estudio corresponde a la segunda etapa, para esto se propuso llevar a cabo una metodología cuasi experimental, cuantitativa, de alcance trasversal donde se analizaron los costos asociados a partidas y costos que eran impactos en el aumento de la resistencia del concreto en comparación con los ahorros presentados en la disminución del tiempo de alquiler de material de encofrado metálico para la obra. Obteniéndose a través de los resultados que lo investigado constituye una generalidad para la obra en estudio, puesto que, en la segunda etapa estudiada de la obra, se encontró un ahorro considerable al realizar la sustitución del concreto, cuando se aumentó la resistencia en las losas. Para el concreto f´c=175 kg/cm2 y 28 días de encofrado se obtuvo un presupuesto global de S/.649,002.46, para f´c=210 kg/cm2 y 28 días de encofrado, S/.650,003.06 y para f´c=245 kg/cm2 y 7 días de encofrado el total ascendió hasta S/.176,634.24. Finalmente se concluyó que, si bien los costos de obra aumentaron un 12% en cuanto al costo del concreto, por otro lado, disminuyó un 25% del costo total en tiempo de desencofrado de elementos horizontales, suponiendo un ahorro considerable en la obra.

The present investigation seeks to optimize the costs on site by reducing the stripping times by increasing the initial resistance of the concrete from 175kg/cm2 to 210 kg/cm2 and 245kg/cm2, in the stripping costs of horizontal elements (solid slabs) in a work carried out during two stages in the city of Ica during the year 2022, of which the study corresponds to the second stage, for this it was proposed to carry out a quasi-experimental, quantitative, cross-sectional methodology where the costs associated with items and costs that were impacts on the increase in the resistance of the concrete in comparison with the savings presented in the decrease in the rental time of metallic formwork material for the work. Obtaining through the results that what was investigated constitutes a generality for the work under study, since, in the second stage studied of the work, considerable savings were found when replacing the concrete, when the resistance in the slabs was increased. For concrete f'c=175 kg/cm2 and 28 days of formwork, a global budget of S/.649,002.46 was obtained, for f'c=210 kg/cm2 and 28 days of formwork, S/.650,003.06 and for f' c=245 kg/cm2 and 7 days of formwork the total amounted to S/.176,634.24. Finally, it was concluded that, although the construction costs increased by 12% in terms of the cost of concrete, on the other hand, the total cost in stripping time of horizontal elements decreased by 25%, representing considerable savings in the work.
Note: Breña
Discipline: Ingeniería Civil
Grade or title grantor: Universidad Privada del Norte. Facultad de Ingeniería
Grade or title: Ingeniero Civil
Juror: Campos Vásquez, Neicer; Vereau Miranda, Edmundo; Rabanal Chávez, Erick Humberto
Register date: 25-Jul-2023; 25-Jul-2023



Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.