Flores, D., (2019). Estudio definitivo de ampliación de una subestación existente 9 MVA 60/25 KV [Trabajo de suficiencia profesional, Universidad Nacional de Ingeniería]. http://hdl.handle.net/20.500.14076/21123
Flores, D., Estudio definitivo de ampliación de una subestación existente 9 MVA 60/25 KV [Trabajo de suficiencia profesional]. PE: Universidad Nacional de Ingeniería; 2019. http://hdl.handle.net/20.500.14076/21123
@misc{renati/711069,
title = "Estudio definitivo de ampliación de una subestación existente 9 MVA 60/25 KV",
author = "Flores Rodríguez, David Oswaldo",
publisher = "Universidad Nacional de Ingeniería",
year = "2019"
}
Title: Estudio definitivo de ampliación de una subestación existente 9 MVA 60/25 KV
Authors(s): Flores Rodríguez, David Oswaldo
Advisor(s): Huayllasco Montalva, Carlos Alberto
Keywords: Subestaciones; Diseño de ampliación; Suministros y montaje
OCDE field: http://purl.org/pe-repo/ocde/ford#2.02.01
Issue Date: 2019
Institution: Universidad Nacional de Ingeniería
Abstract: El presente trabajo describe los aspectos a considerar para el diseño de ampliación de subestaciones existentes con la finalidad de evitar riesgos durante el desarrollo del proyecto.
En el caso particular, se desarrollan los estudios de ingeniería a nivel definitivo para la ampliación de transformación de una subestación de 60 kV con una celda de transformación de 9 MVA 60/25 kV, la cual tiene restricciones de espacio y celdas no proyectadas, para lo cual se plantea el uso de equipos de patio híbridos compactos, que reducen notablemente el requerimiento de espacios y los tiempos de montaje y puesta en servicio.
El documento detalla las consideraciones para del diseño y criterios para la ampliación de las subestaciones en general, teniendo como base la adecuada relación con las instalaciones existentes, con el fin de garantizar la adecuada integración de los equipos de patio, protección, control y comunicaciones de la subestación. Asimismo, se indican las características técnicas de la ampliación de la subestación, tanto para el suministro y montaje, además de los cronogramas y presupuestos requeridos para la ejecución del proyecto.
Finalmente permite determinar los detalles de ingeniería y costos para la ejecución de la ampliación de la subestación, considerando las especificación y recomendaciones de las normas vigentes y garantizar la adecuada operación del sistema, que son controladas por los organismos normativos y reguladores del país.
This document describes the aspects to consider for the design of expansion of existing substations in order to avoid risks during the development of the project. In the particular case, engineering studies are developed at a definitive level for the extension of the power transformation of a 60 kV substation with a transformation bay of 9 MVA 60/25 kV, which has not considered much free space for future bays in the initial project. In that case the compact hybrid switchgear is proposed like a solution, which significantly reduces the space requirement, assembly times and commissioning times. In general, this work explains the considerations for design and criteria for the expansión of substations, based on the appropriate relationship with existing infrastructure, in order to ensure the proper integration of switchyard equipment, protection, control and communications. Likewise, the technical characteristics of the extension of the substation are indicated, both for the supply and assembly, in addition to the schedules and budgets required for the execution of the project. Finally, it allows to determine the engineering and costs for the execution of the extension of the substation, considering the specification and recommendations of the current laws and guaranteeing the proper operation of the power systems, which are controlled by the Regulation organism of the country.
This document describes the aspects to consider for the design of expansion of existing substations in order to avoid risks during the development of the project. In the particular case, engineering studies are developed at a definitive level for the extension of the power transformation of a 60 kV substation with a transformation bay of 9 MVA 60/25 kV, which has not considered much free space for future bays in the initial project. In that case the compact hybrid switchgear is proposed like a solution, which significantly reduces the space requirement, assembly times and commissioning times. In general, this work explains the considerations for design and criteria for the expansión of substations, based on the appropriate relationship with existing infrastructure, in order to ensure the proper integration of switchyard equipment, protection, control and communications. Likewise, the technical characteristics of the extension of the substation are indicated, both for the supply and assembly, in addition to the schedules and budgets required for the execution of the project. Finally, it allows to determine the engineering and costs for the execution of the extension of the substation, considering the specification and recommendations of the current laws and guaranteeing the proper operation of the power systems, which are controlled by the Regulation organism of the country.
Link to repository: http://hdl.handle.net/20.500.14076/21123
Discipline: Ingeniería Eléctrica
Grade or title grantor: Universidad Nacional de Ingeniería. Facultad de Ingeniería Eléctrica y Electrónica
Grade or title: Ingeniero Electricista
Juror: Rosado Aguirre, Estanislao Ubaldo
Register date: 22-Sep-2021