Bibliographic citations
This is an automatically generated citacion. Modify it if you see fit
Paucar, Y., (2019). Envolvente operativa aplicada a pozos productores de gas de la cuenca Ucayali [Tesis, Universidad Nacional de Ingeniería]. http://hdl.handle.net/20.500.14076/20668
Paucar, Y., Envolvente operativa aplicada a pozos productores de gas de la cuenca Ucayali [Tesis]. PE: Universidad Nacional de Ingeniería; 2019. http://hdl.handle.net/20.500.14076/20668
@misc{renati/710985,
title = "Envolvente operativa aplicada a pozos productores de gas de la cuenca Ucayali",
author = "Paucar Berrocal, Yul Junior",
publisher = "Universidad Nacional de Ingeniería",
year = "2019"
}
Title: Envolvente operativa aplicada a pozos productores de gas de la cuenca Ucayali
Authors(s): Paucar Berrocal, Yul Junior
Advisor(s): Navarro Cornejo, William Romeo
Keywords: Diseño de pozos; Envolventes; Gas
OCDE field: http://purl.org/pe-repo/ocde/ford#2.07.03
Issue Date: 2019
Institution: Universidad Nacional de Ingeniería
Abstract: Esta tesis tiene como objetivo el desarrollo y aplicación de la metodología de envolvente operativa para evaluar la adecuada operación de los pozos productores, así como la variación en el tiempo. Un ejemplo de aplicación es evaluar si es necesario un cambio de completación en los pozos productores. Lo anterior permite una operación continua que puede garantizar el caudal de entrega del campo hasta su abandono, esto es de suma importancia considerando que la producción de Camisea representa el 95% de la producción nacional de gas en el Perú.
Esta tesis se dividió en cuatro capítulos: Introducción, procedimiento de trabajo, aplicación y por último conclusiones y recomendaciones. El procedimiento de trabajo fue dividido en diez partes o etapas las cuales fueron: selección de pozos a analizar y recolección de la información, determinación del IPR con presiones de fondo, selección de la correlación de flujo multifásico “VLP”, match IPR-VLP, curva de carga de líquidos, curva de erosión, envolvente operativa de pozos, balance de materia, evaluación de la envolvente operativa en tiempo, y por último la envolvente operativa de pozo con presiones de cabeza de pozo.
Se usó el software PROSPER para obtener los datos para generar la curva de carga de líquidos y curva de erosión que sumada a la IPR generada con presiones de fondo generan la “Envolvente Operativa” que fue evaluada en el tiempo con ayuda del balance de materiales.
Para obtener la curva de carga de líquidos, PROPER usa la ecuación de Turner et al. y para la curva de erosión usa la ecuación planteada en la API RP 14E, en esta tesis el factor “C” usado en dicha ecuación planteada es de 123 por ser tubería de producción de acero al carbono.
Adicionalmente el IPR fue generada con datos de los sensores de presión de cabeza y caudal de gas obtenidos del medidor multifásico, las presiones de cabeza fueron usadas debido a que son los datos disponibles en forma continua en la operación del pozo. El método de Fetkovich fue usado para generar el IPR.
Esta “Envolvente operativa “fue aplicada para tres pozos productores de gas de la cuenca Ucayali”
This thesis has as objective to develop and to apply the methodology of operative envelope to evaluate the right operation of gas producing wells, and its variation in time. One example of application is to evaluate if it is necessary a change in the well completion of the gas producing wells. The above allows a continuous operation that can guarantee the deliverability of the field until its abandonment, this is of great importance considering that Camisea production represents 95% of the national production of gas in Peru. This thesis was divided in four chapters: Introduction, work procedure, application and last conclusions and recommendations. Work procedure was divided in ten parts or stages: selection of wells to analyze and gathering of information, determination of the IPR using downhole pressure, selection of correlation of multiphase flow “VLP”, match of IPR and VLP, liquid loading curve, erosion curve, material balance, evaluation of the operative envelope in time, and last the operative envelope using wellhead pressures. The software PROSPER was used to get the data to generate the la liquid loading curve and the erosion curve which added to the IPR generate with bottom hole pressures, generate the Operative Envelope” that was evaluated in time with help of material balance. To get the liquid loading curve, PROSPER use the equation of Turner et al and to get the erosion curve use the equation of API RP 14E, in this thesis the C factor used in that equation of API RP 14E is 123 due to the production tubing is of carbon steel. Additionally, the IPR was generated with data of wellhead pressure gauges and gas rate got from multiphase flow meters, wellhead pressures were used because that is the data available in operations. Fetkovich method was used to generate the IPR. This “Operative Envelope” was applied to three producers gas wells of the Ucayali basin.
This thesis has as objective to develop and to apply the methodology of operative envelope to evaluate the right operation of gas producing wells, and its variation in time. One example of application is to evaluate if it is necessary a change in the well completion of the gas producing wells. The above allows a continuous operation that can guarantee the deliverability of the field until its abandonment, this is of great importance considering that Camisea production represents 95% of the national production of gas in Peru. This thesis was divided in four chapters: Introduction, work procedure, application and last conclusions and recommendations. Work procedure was divided in ten parts or stages: selection of wells to analyze and gathering of information, determination of the IPR using downhole pressure, selection of correlation of multiphase flow “VLP”, match of IPR and VLP, liquid loading curve, erosion curve, material balance, evaluation of the operative envelope in time, and last the operative envelope using wellhead pressures. The software PROSPER was used to get the data to generate the la liquid loading curve and the erosion curve which added to the IPR generate with bottom hole pressures, generate the Operative Envelope” that was evaluated in time with help of material balance. To get the liquid loading curve, PROSPER use the equation of Turner et al and to get the erosion curve use the equation of API RP 14E, in this thesis the C factor used in that equation of API RP 14E is 123 due to the production tubing is of carbon steel. Additionally, the IPR was generated with data of wellhead pressure gauges and gas rate got from multiphase flow meters, wellhead pressures were used because that is the data available in operations. Fetkovich method was used to generate the IPR. This “Operative Envelope” was applied to three producers gas wells of the Ucayali basin.
Link to repository: http://hdl.handle.net/20.500.14076/20668
Discipline: Ingeniería de Petróleo y Gas Natural
Grade or title grantor: Universidad Nacional de Ingeniería. Facultad de Ingeniería de Petróleo, Gas Natural y Petroquímica
Grade or title: Ingeniero de Petróleo y Gas Natural
Juror: Argumé Chávez, Edgard Américo
Register date: 13-Jul-2021