Bibliographic citations
This is an automatically generated citacion. Modify it if you see fit
Cruzado, H., (2022). Business consulting – Ibe Contratistas Generales S.A.C. [Pontificia Universidad Católica del Perú]. http://hdl.handle.net/20.500.12404/22242
Cruzado, H., Business consulting – Ibe Contratistas Generales S.A.C. []. PE: Pontificia Universidad Católica del Perú; 2022. http://hdl.handle.net/20.500.12404/22242
@mastersthesis{renati/532529,
title = "Business consulting – Ibe Contratistas Generales S.A.C.",
author = "Cruzado Cajan, Hector Giancarlo",
publisher = "Pontificia Universidad Católica del Perú",
year = "2022"
}
Full metadata record
Núñez Morales, Nicolás Andrés
Cruzado Cajan, Hector Giancarlo
2022-05-02T23:16:09Z
2022-05-02T23:16:09Z
2022
2022-05-02
http://hdl.handle.net/20.500.12404/22242
Ibe Contratistas Generales S.A.C. es una organización de capital peruano que se
ha enfocado en el sector inmobiliario y construcción, y cuenta con más de 13 años de
amplia experiencia en el rubro por todos los servicios que ofrece. El objetivo de la
presente consultoría fue de identificar el problema clave que no le está permitiendo a
Ibe Contratistas Generales alcanzar los márgenes de rentabilidad esperados, y cumplir
con lo estipulado en los contratos ganados correspondientes a las licitaciones
participadas. Por ello, se han analizado las principales causas que generan el problema
identificado, en base al estudio interno realizado y a las entrevistas y reuniones con el
equipo estratégico de Ibe Contratistas Generales S.A.C. Por otro lado, se encontró que
la causa raíz del problema está relacionada al crecimiento del presupuesto designado al
levantamiento de observaciones en obra, esto como producto de una insuficiente
revisión e interpretación de expedientes y planos, así como también, al insuficiente
personal para el seguimiento y control de calidad y la falta de comunicación entre las
áreas.
En la presente consultoría se proponen iniciativas para reforzar la gestión de la
construcción, a través de la implementación del software Fieldwire, y con ello la
posibilidad de visualizar en tiempo real de todas las observaciones producidas, el
seguimiento y control de las tareas asignadas para el levantamiento de observaciones. El
costo total de la implementación del software es de S/ 102,658.08 y se espera lograr
ahorros hasta en 18% correspondientes al presupuesto de Calidad, es decir, S/59,760,70.
Con respecto al ahorro en observaciones no planificadas, se espera ahorrar hasta en un
S/ 671,562.24, es decir, 3% de reducción en un escenario optimista. Lo anteriormente
mencionado conllevará a que la empresa alcance sus objetivos de rentabilidad y logre la
sostenibilidad deseada en el tiempo. (es_ES)
Ibe General Contractors S.A.C. is a Peruvian capital organization that has
focused on the real estate and construction sector, and has more than 13 years of
extensive experience in the field for all the services it offers. The objective of this
consultancy was to identify the key problem that is not allowing Ibe Contratistas
Generales to reach the expected profit margins, and to comply with the provisions of the
contracts won corresponding to the participated tenders. For this reason, the main causes
that generate the identified problem have been analyzed, based on the internal study
carried out and the interviews and meetings with the strategic team of Ibe Contratistas
Generales S.A.C. On the other hand, it was found that the root cause of the problem is
related to the growth of the budget allocated to the collection of observations on site,
this as a result of insufficient review and interpretation of files and plans, as well as
insufficient personnel for follow-up. and quality control and the lack of communication
between the areas.
In this consultancy, initiatives are proposed to reinforce construction
management, through the implementation of Fieldwire software, and with it the
possibility of visualizing in real time all the observations produced, the monitoring and
control of the tasks assigned for the Rising observations. The total cost of software
implementation is S/ 102,658.08 and it is expected to achieve savings of up to 18%
corresponding to the quality budget, that is, S/ 59,760.70. With regard to savings in
unplanned observations, it is expected to save up to S/ 671,562.24, that is, a 3%
reduction in an optimistic scenario. The aforementioned will lead to the company
reaching its profitability objectives and achieving the desired sustainability over time. (es_ES)
spa (es_ES)
Pontificia Universidad Católica del Perú (es_ES)
info:eu-repo/semantics/closedAccess (es_ES)
Industria de la construcción--Administración (es_ES)
Consultores de empresas--Planificación estratégica (es_ES)
Empresas inmobiliarias--Perú (es_ES)
Innovaciones tecnológicas--Administración (es_ES)
Business consulting – Ibe Contratistas Generales S.A.C. (es_ES)
info:eu-repo/semantics/masterThesis (es_ES)
Pontificia Universidad Católica del Perú. CENTRUM (es_ES)
Administración Estratégica de Empresas (es_ES)
Maestría (es_ES)
Maestro en Administración Estratégica de Empresas (es_ES)
PE (es_ES)
https://purl.org/pe-repo/ocde/ford#5.02.04 (es_ES)
https://purl.org/pe-repo/renati/level#maestro (es_ES)
49011442
https://orcid.org/0000-0003-2193-3830 (es_ES)
47518651
413307 (es_ES)
Igor Leopoldo Loza Geldres (es_ES)
Kelly Rojas Valdez (es_ES)
https://purl.org/pe-repo/renati/type#tesis (es_ES)
Privada asociativa
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.