Neyra Torres, Jose Luis
Segura Castañeda, Jorge Luis
Tapia Sullca, Jenifer Marina Teresa
2023-07-25T17:22:27Z
2023-07-25T17:22:27Z
2023-07-19
Segura, J. L., & Tapia, J. M. (2022). Optimización de costos en obra mediante la reducción de plazos de desencofrado al aumentar resistencia inicial de concreto, Ica, 2022 [Tesis de licenciatura, Universidad Privada del Norte]. Repositorio de la Universidad Privada del Norte. https://hdl.handle.net/11537/33868 (es_PE)
620.112 SEGU 2022 (es_PE)
https://hdl.handle.net/11537/33868
La presente investigación busca optimizar los costos en obra mediante la reducción de plazos de desencofrado al aumentar resistencia inicial del concreto de 175kg/cm2 a 210 kg/cm2 y 245kg/cm2, en los costos de desencofrado de elementos horizontales (losas macizas) en una obra realizada durante dos etapas en la ciudad de Ica durante el año 2022, de las que el estudio corresponde a la segunda etapa, para esto se propuso llevar a cabo una metodología cuasi experimental, cuantitativa, de alcance trasversal donde se analizaron los costos asociados a partidas y costos que eran impactos en el aumento de la resistencia del concreto en comparación con los ahorros presentados en la disminución del tiempo de alquiler de material de encofrado metálico para la obra. Obteniéndose a través de los resultados que lo investigado constituye una generalidad para la obra en estudio, puesto que, en la segunda etapa estudiada de la obra, se encontró un ahorro considerable al realizar la sustitución del concreto, cuando se aumentó la resistencia en las losas. Para el concreto f´c=175 kg/cm2 y 28 días de encofrado se obtuvo un presupuesto global de S/.649,002.46, para f´c=210 kg/cm2 y 28 días de encofrado, S/.650,003.06 y para f´c=245 kg/cm2 y 7 días de encofrado el total ascendió hasta S/.176,634.24. Finalmente se concluyó que, si bien los costos de obra aumentaron un 12% en cuanto al costo del concreto, por otro lado, disminuyó un 25% del costo total en tiempo de desencofrado de elementos horizontales, suponiendo un ahorro considerable en la obra. (es_PE)
The present investigation seeks to optimize the costs on site by reducing the stripping times by increasing the initial resistance of the concrete from 175kg/cm2 to 210 kg/cm2 and 245kg/cm2, in the stripping costs of horizontal elements (solid slabs) in a work carried out during two stages in the city of Ica during the year 2022, of which the study corresponds to the second stage, for this it was proposed to carry out a quasi-experimental, quantitative, cross-sectional methodology where the costs associated with items and costs that were impacts on the increase in the resistance of the concrete in comparison with the savings presented in the decrease in the rental time of metallic formwork material for the work. Obtaining through the results that what was investigated constitutes a generality for the work under study, since, in the second stage studied of the work, considerable savings were found when replacing the concrete, when the resistance in the slabs was increased. For concrete f'c=175 kg/cm2 and 28 days of formwork, a global budget of S/.649,002.46 was obtained, for f'c=210 kg/cm2 and 28 days of formwork, S/.650,003.06 and for f' c=245 kg/cm2 and 7 days of formwork the total amounted to S/.176,634.24. Finally, it was concluded that, although the construction costs increased by 12% in terms of the cost of concrete, on the other hand, the total cost in stripping time of horizontal elements decreased by 25%, representing considerable savings in the work. (es_PE)
Tesis (es_PE)
application/pdf (es_PE)
application/msword (es_PE)
spa (es_PE)
Universidad Privada del Norte (es_PE)
info:eu-repo/semantics/restrictedAccess (es_PE)
Universidad Privada del Norte (es_PE)
Repositorio Institucional - UPN (es_PE)
Control de gestión (es_PE)
Resistencia de materiales (es_PE)
Concreto armado (es_PE)
Encofrado (es_PE)
Resistencia (es_PE)
Elementos horizontales de concreto (es_PE)
Costos (es_PE)
Formwork (es_PE)
Resistance (es_PE)
Horizontal concrete elements (es_PE)
Costs (es_PE)
Optimización de costos en obra mediante la reducción de plazos de desencofrado al aumentar resistencia inicial de concreto, Ica, 2022 (es_PE)
info:eu-repo/semantics/bachelorThesis (es_PE)
Universidad Privada del Norte. Facultad de Ingeniería (es_PE)
Ingeniería Civil (es_PE)
Título Profesional (es_PE)
Ingeniero Civil (es_PE)
PE (es_PE)
https://purl.org/pe-repo/ocde/ford#2.01.01 (es_PE)
Pregrado (es_PE)
http://purl.org/pe-repo/renati/level#tituloProfesional (es_PE)
21454204
https://orcid.org/0000-0002-6470-2998 (es_PE)
45092588
46789195
732016 (es_PE)
Vereau Miranda, Edmundo
Rabanal Chávez, Erick Humberto
Campos Vásquez, Neicer
http://purl.org/pe-repo/renati/type#tesis (es_PE)
Privada societaria



IMPORTANTE
La información contenida en este registro es de entera responsabilidad de la universidad, institución o escuela de educación superior que administra el repositorio académico digital donde se encuentra el trabajo de investigación y/o proyecto, los cuales son conducentes a optar títulos profesionales y grados académicos. SUNEDU no se hace responsable por los contenidos accesibles a través del Registro Nacional de Trabajos de Investigación – RENATI.