Bibliographic citations
Pérez, Y., (2024). Implementación del sistema Last Planner en la ejecución del proyecto “Rehabilitación del local escolar N° 14125 de la localidad Chaquira”, Piura [Tesis, Universidad Privada Antenor Orrego]. https://hdl.handle.net/20.500.12759/39871
Pérez, Y., Implementación del sistema Last Planner en la ejecución del proyecto “Rehabilitación del local escolar N° 14125 de la localidad Chaquira”, Piura [Tesis]. PE: Universidad Privada Antenor Orrego; 2024. https://hdl.handle.net/20.500.12759/39871
@misc{renati/499740,
title = "Implementación del sistema Last Planner en la ejecución del proyecto “Rehabilitación del local escolar N° 14125 de la localidad Chaquira”, Piura",
author = "Pérez Vásquez, Yuliana De Jesús",
publisher = "Universidad Privada Antenor Orrego",
year = "2024"
}
The objective of this research was to implement planning in the execution phase using the Last Planner System in the civil work Local Escolar No. 14125 in the town of Chaquira. Therefore, the focus of the study was mixed, descriptive level and experimental, cross-sectional design. Our sample was all the professional and technical staff of the project “Rehabilitation of school premises No. 44125 in the town of Chaquira, district of Arena – Piura”. Based on the results, a master plan was designed that began with training and designation of staff responsibilities in each of the processes. Then, planning was carried out using Lookahead Planning for the work of school premises 14125. Also, weekly planning was carried out for the educational project, the construction processes were identified during the execution of the school premises to meet the deadline, cost and quality of the work; and the percentage of the compliance plan (PPC) of the planned activities during the execution of the work was verified. It was concluded that, by implementing Last Planner System, planning was improved since the project was completed within the time established in the work contract.