Title: Mejora de la eficiencia en el proceso de despacho de materiales mediante la aplicación de herramientas Lean Warehousing en una empresa constructora
Other Titles: Improved efficiency in the material dispatch process through the application of lean warehousing tools in a construction company
Advisor(s): Llontop Jesús, José Alberto
OCDE field: https://purl.org/pe-repo/ocde/ford#2.11.04; https://purl.org/pe-repo/ocde/ford#2.00.00
Issue Date: 16-Nov-2023
Institution: Universidad Peruana de Ciencias Aplicadas (UPC)
Abstract: Los almacenes tienen un impacto global en toda la cadena de suministro, pero muchas veces no reciben el tiempo ni el análisis que merecen, normalmente porque no representan la parte principal de las actividades de la empresa, sino que cumplen una función de apoyo. El presente proyecto tiene como objetivo reducir los tiempos en la atención de suministro de materiales en una empresa constructora a fin de incrementar la eficiencia en la gestión de almacén. Actualmente, presenta problemas en el proceso de gestión y atención de vales de despacho de materiales, ello debido a tiempos improductivos en transporte, procesos inapropiados y movimientos innecesarios. Para la identificación del problema, se ejecutó un Value Stream Map (VSM) al proceso con la finalidad de diagnosticar los tiempos de ciclo, obteniendo un lead time del proceso de 37 min/vale y una eficiencia del 35.59%. La propuesta de mejora incluye la aplicación de las 5s, análisis ABC y rediseño de layout como herramientas de Lean Warehousing y el uso de un sistema de gestión de almacén para disminuir tiempos improductivos, procesos inapropiados y movimientos innecesarios. Los resultados obtenidos a partir de lo propuesto mostraron que la eficiencia aumentó de 35.59% a 71.85%, el lead time del proceso de 37 min/vale a 5 min/vale, un aprovechamiento del espacio de almacén de 49.78% a 27.23%, la exactitud de registro de inventario de 33.33% a 84.6%. Además, el análisis costo-beneficio de esta propuesta es 1.38, lo que la hace viable.

Warehouses have a global impact on the entire supply chain, but they are often not given the time or analysis they deserve, usually because they are not the core part of the company's activities, but serve a support function. The objective of this project is to reduce the time in the supply of materials in a construction company in order to increase efficiency in warehouse management and save costs. Currently, it presents problems in the process of management and attention of material dispatch vouchers, due to unproductive times in transportation, inappropriate processes and unnecessary movements. To identify the problem, a Value Stream Map (VSM) was performed on the process in order to diagnose the cycle times, obtaining a process lead time of 37 min/voucher and an efficiency of 35.59%. The improvement proposal includes the application of the 5s, ABC analysis and layout redesign as Lean Warehousing tools and the use of a warehouse management system to reduce unproductive times, inappropriate processes and unnecessary movements. The results obtained from the proposal showed that efficiency increased from 35.59% to 71.85%, process lead time from 37 min/voucher to 5 min/voucher, warehouse space utilization from 49.78% yo 27.23%, inventory record accuracy from 33.33% to 84.6%. In addition, the cost-benefit analysis of this proposal is 1.38, which makes it viable.
Discipline: Ingeniería Industrial
Grade or title grantor: Universidad Peruana de Ciencias Aplicadas (UPC). División de Estudios Profesionales para Ejecutivos (EPE)
Grade or title: Ingeniero industrial
Juror: Jose Alberto Llontop Jesus; Daniela Rocio Duran Tinoco
Register date: 25-Jan-2024



This item is licensed under a Creative Commons License Creative Commons