Look-up in Google Scholar
Title: Propuesta para incrementar la disponibilidad de una central solar generadora de energía eléctrica usando TPM y RCM en la gestión del mantenimiento
Other Titles: Proposal to Increase the Availability of a Solar Power Plant Using TPM and RCM in Maintenance Management
Advisor(s): LLontop Jesús, José Alberto
OCDE field: http://purl.org/pe-repo/ocde/ford#2.00.00; https://purl.org/pe-repo/ocde/ford#2.11.04
Issue Date: 15-Dec-2022
Institution: Universidad Peruana de Ciencias Aplicadas (UPC)
Abstract: El estudio analiza un problema de cumplimiento de disponibilidad en una Planta Solar Fotovoltaica generadora de energía eléctrica, como fuente de estudio se tomó la data de fallas y producción desde el año 2018 hasta el 2020. Durante el análisis de causas se identifica que el problema se origina en la baja confiabilidad de equipos evidenciada por la alta tasa de fallas de diversos componentes. En ese sentido, se seleccionó el TPM (Mantenimiento Productivo Total) como metodología central para el diseño del modelo de solución, se consideran diversas acciones sostenidas en los pilares del TPM y distribuidas en tres etapas que son la planificación, la ejecución y la sostenibilidad en el tiempo. Se incluye el uso del RCM (Mantenimiento Basado en Confiabilidad) como catalizador para potenciar los planes de mantenimiento, cuyos entregables definirán las tareas de mantenimiento y frecuencias de ejecución que serán gestionadas mediante los pilares del TPM como el mantenimiento autónomo, mantenimiento preventivo y la planificación del mantenimiento correctivo; también se destaca el uso del pilar de mejoras enfocadas que permitió plantear soluciones dedicadas a diferentes problemas. Finalmente, la propuesta en su conjunto fue implementada durante el año 2021 y se obtuvieron las siguientes variaciones con respecto al año 2020, incremento de disponibilidad de 97.59% a 98.41%, incremento de producción de energía de 432.34 GWh a 440.08 GWh; así mismo, este incremento de energía permitirá una disminución de 3 922.57 toneladas de CO2 al año.

The study analyzes an availability compliance problem in a Photovoltaic Solar Power Plant in the Moquegua. The data from 2018 to 2020 is taken as a source of study. During the analysis of causes, it is identified that the problem originates from the low reliability of equipment evidenced by the high failure rate of various components. For this reason, the TPM (Total Productive Maintenance) was selected as the central methodology for the design of the solution model, considering various actions sustained in the pillars of the TPM and distributed in three stages that are planning, execution and sustainability. The use of RCM (Reliability Based Maintenance) is included as a catalyst to promote maintenance plans, whose output documents will define the maintenance tasks and execution frequencies that will be managed through the TPM pillars such as autonomous maintenance, preventive maintenance, and planning. corrective maintenance: The use of the focused improvements pillar is also highlighted, which allowed us to propose solutions dedicated to different problems. Finally, the proposal as a whole was implemented during the year 2021 and the following variations were obtained with respect to the year 2020, increase in availability from 97.59% to 98.41%, increase in energy production from 432.34 GWh to 440.08 GWh; Likewise, this increase in energy will allow a reduction of 3,922.57 tons of CO2 per year.
Discipline: Ingeniería Industrial
Grade or title grantor: Universidad Peruana de Ciencias Aplicadas (UPC). División de Estudios Profesionales para Ejecutivos (EPE)
Grade or title: Ingeniero Industrial
Juror: Salas Castro, Rosa Fernanda; Viacava Campos, Gino Evangelista; Chavez Soriano, Pedro Alberto
Register date: 16-May-2023



This item is licensed under a Creative Commons License Creative Commons