Granda, R., Okumura, G. (2021). Estudio de prefactibilidad para la producción de bicicletas eléctricas plegables [Universidad de Lima]. https://hdl.handle.net/20.500.12724/14743
Granda, R., Okumura, G. Estudio de prefactibilidad para la producción de bicicletas eléctricas plegables []. PE: Universidad de Lima; 2021. https://hdl.handle.net/20.500.12724/14743
@misc{renati/234716,
title = "Estudio de prefactibilidad para la producción de bicicletas eléctricas plegables",
author = "Okumura Hosaka, Gabriela",
publisher = "Universidad de Lima",
year = "2021"
}
Title: Estudio de prefactibilidad para la producción de bicicletas eléctricas plegables
Advisor(s): Paredes Larroca, Fabricio Humberto
Keywords: Bicicletas eléctricas; Transporte sostenible; Transporte urbano; Aspectos ambientales; Proyectos industriales; Estudios de prefactibilidad
OCDE field: https://purl.org/pe-repo/ocde/ford#2.11.04
Issue Date: 2021
Institution: Universidad de Lima
Abstract: El presente estudio preliminar para la implementación de una planta productora de
bicicletas eléctricas plegables busca determinar la viabilidad de mercado, técnica,
económica y financiera.
La demanda del proyecto para el primer año es de 861 bicicletas. Debido al
cambio cultural (preferencia de medios de transporte limpios), ser un producto que
contribuye a aliviar la problemática del tráfico, con el distanciamiento social y la
conservación del medio ambiente, se considera una buena aceptación por el público
objetivo. Asimismo, como resultado de las encuestas realizadas, se obtuvo que el 89% de
las personas encuestadas estarían dispuestas a adquirir el producto propuesto y una
intensidad de compra de 68.1%.
Se determinó que la planta se ubicará en Lima Metropolitana, en el distrito de Ate.
El tamaño de planta estará determinado por la relación tamaño-tecnología
equivalente a 4,209 bicicletas. El punto de equilibrio sería 817 bicicletas y el cuello de
botella sería la operación de pintado.
Para determinar el proceso de producción se realizó una evaluación de costos y
complejidad entre producir o tercerizar la fabricación del marco de la bicicleta. Al ser
actividades muy especializadas y con equipos costosos, se optó por tercerizar. Con el
marco fabricado, quedarían las actividades de control de calidad, perforado, pulido,
soldado, imprimado, pintado, curado, enfriado y ensamblado.
El área total calculada es 491.9 m2
.
La inversión del proyecto asciende a S/. 528,422.7 y presenta una estructura de
55% aporte propio y 45% financiamiento con el Banco Interamericano de Finanzas por
5 años a una TEA de 11.59%, tasa asignada para préstamos a PYMES.
De la evaluación económica y financiera del proyecto, se obtiene un TIR
económico de 43% con período de recupero de 3 años y 3 meses; y un TIR financiero de
57% con un periodo de recupero de 2 años y 10 meses.
This preliminary study for the implementation of a folding electric bicycle production plant looks for determine the market, technical, economic and financial viability. The project demand for the first year is 861 bicycles. Due to the cultural change (preference for clean means of transport), being a product that contributes to alleviating the problem of traffic, with social distancing and conservation of the environment, is considered a good acceptance by the target market. Likewise, as result of the surveys carried out, it was obtained that 89% of the people surveyed would be willing to purchase the proposed product and a purchase intensity of 68.1%. It was determined that the plant will be located in Metropolitan Lima, in the Ate district. The size of the plant will be determined by the size-technology ratio equivalent to 4,209 bicycles. The breakeven point would be 817 bikes and the bottleneck would be the painting operation. To determine the production process, an evaluation of costs and complexity was carried out between producing or outsourcing the manufacture of the bicycle frame. Being very specialized activities and with expensive equipment, it would be better to outsource. With the frame manufactured, the activities of quality control, drilling, polishing, welding, priming, painting, heat treatment, cooling and assembly will remain. The total area determined is 491.9 m2. The investment of the project amounts to S /. 528,422.7 and presents a structure of 55% own contribution and 45% financing with the Inter-American Finance Bank for 5 years at a TEA of 11.59%, the rate assigned for loans to SMEs. From the economic and financial evaluation of the project, an economic IRR of 43% is obtained with a recovery period of 3 years and 3 months; and a financial IRR of 57% with a payback period of 2 years and 10 months.
This preliminary study for the implementation of a folding electric bicycle production plant looks for determine the market, technical, economic and financial viability. The project demand for the first year is 861 bicycles. Due to the cultural change (preference for clean means of transport), being a product that contributes to alleviating the problem of traffic, with social distancing and conservation of the environment, is considered a good acceptance by the target market. Likewise, as result of the surveys carried out, it was obtained that 89% of the people surveyed would be willing to purchase the proposed product and a purchase intensity of 68.1%. It was determined that the plant will be located in Metropolitan Lima, in the Ate district. The size of the plant will be determined by the size-technology ratio equivalent to 4,209 bicycles. The breakeven point would be 817 bikes and the bottleneck would be the painting operation. To determine the production process, an evaluation of costs and complexity was carried out between producing or outsourcing the manufacture of the bicycle frame. Being very specialized activities and with expensive equipment, it would be better to outsource. With the frame manufactured, the activities of quality control, drilling, polishing, welding, priming, painting, heat treatment, cooling and assembly will remain. The total area determined is 491.9 m2. The investment of the project amounts to S /. 528,422.7 and presents a structure of 55% own contribution and 45% financing with the Inter-American Finance Bank for 5 years at a TEA of 11.59%, the rate assigned for loans to SMEs. From the economic and financial evaluation of the project, an economic IRR of 43% is obtained with a recovery period of 3 years and 3 months; and a financial IRR of 57% with a payback period of 2 years and 10 months.
Link to repository: https://hdl.handle.net/20.500.12724/14743
Discipline: Ingeniería Industrial
Grade or title grantor: Universidad de Lima. Facultad de Ingeniería y Arquitectura
Grade or title: Ingeniero Industrial
Juror: Arroyo Gordillo, Pedro Antonio; Ferrer Aspillaga, Gerardo Maria Martin; Rojas iriarte, Juan nrique
Register date: 15-Dec-2021