Colqui, D., Ruiz, R. (2016). Propuesta metodológica de costos unitarios utilizando la metodología Last Planner System [Tesis, Universidad Privada Antenor Orrego]. https://hdl.handle.net/20.500.12759/2098
Colqui, D., Ruiz, R. Propuesta metodológica de costos unitarios utilizando la metodología Last Planner System [Tesis]. PE: Universidad Privada Antenor Orrego; 2016. https://hdl.handle.net/20.500.12759/2098
@misc{renati/1350009,
title = "Propuesta metodológica de costos unitarios utilizando la metodología Last Planner System",
author = "Ruiz Venegas, Robin Paul",
publisher = "Universidad Privada Antenor Orrego",
year = "2016"
}
Title: Propuesta metodológica de costos unitarios utilizando la metodología Last Planner System
Authors(s): Colqui Rojas, David Daniel; Ruiz Venegas, Robin Paul
Advisor(s): Vargas Cardenas, Carlos Manuel
Keywords: Costos unitarios; Metodología Last Planner System
OCDE field: https://purl.org/pe-repo/ocde/ford#2.01.00
Issue Date: 2016
Institution: Universidad Privada Antenor Orrego
Abstract: Esta tesis enfocada a la rama de gestión de proyectos, para su desarrollo los
datos han sido recopilados, atreves de la observación directa y encuestas a
profundidad, en la obra Multifamiliar Luzmila III, proyecto ejecutado por la
constructora e inmobiliaria Tc Antares S.A.C. Tiene como objetivo principal
contribuir a que las empresas constructoras cuenten con una metodología de
análisis de costos unitarios en la que se incluye la metodología last planner
sytem (Sistema del Último Planificador) de la filosofía Lean Construction
(Construcción sin Pérdidas), con la que se pretende que los encargados de la
elaboración de presupuestos puedan tener una mejor precisión al momento
de elaborar sus costos unitarios, sobre todo en la mano de obra.
Centrados en el costo directo del presupuesto y la programación maestra de
la Obra antes mencionada, la propuesta consiste básicamente en dividir los
costos unitarios de las partidas ejecutadas en costo fijo; que serán
considerados todos los materiales e insumos que se necesiten para culminar
las partidas, y costo Variable; que serán considerados la mano de Obra y los
Equipos involucrados en cada partida ejecutada. Simultáneamente se aplicó
la metodología Last Planner Sytem (Sistema del último planificador) a la
programación general de la obra, obteniendo como resultados los Lookahead
de Producción (Planificación Intermedia de Producción) y los Lookahead de
Materiales (Planificación Intermedia de Materiales), con estos últimos se logró
calcular la eficiencia de cada partida ejecutada durante el tiempo que se
tomaron los datos.
This thesis focused on project management branch for their development data have been collected, dare direct observation and in-depth surveys in the work Multifamily Ludmila III, a project implemented by the construction and real estate Tc SAC Antares Its main objective is to contribute to the construction companies have a methodology of analysis of unit costs in the last planner methodology sytem (Last Planner System) philosophy of Lean Construction (Building without loss) is included, with which It intended to be responsible for budgeting can have a better precision when preparing their unit costs, especially labor. Focused on the direct cost budget and master scheduling of the aforementioned work, the proposal is basically split unit costs of items carried in fixed cost; to be considered all materials and supplies needed to complete the items, and variable costs; that will be considered labor and equipment involved in each game executed. Last Planner methodology simultaneously Sytem (Last Planner System) from the general program of work was applied, obtaining as results the Lookahead Production (Intermediate Production Planning) and Lookahead Materials (Intermediate Materials Planning), with the latter it was possible to calculate the efficiency of each item executed during the time the data were collected.
This thesis focused on project management branch for their development data have been collected, dare direct observation and in-depth surveys in the work Multifamily Ludmila III, a project implemented by the construction and real estate Tc SAC Antares Its main objective is to contribute to the construction companies have a methodology of analysis of unit costs in the last planner methodology sytem (Last Planner System) philosophy of Lean Construction (Building without loss) is included, with which It intended to be responsible for budgeting can have a better precision when preparing their unit costs, especially labor. Focused on the direct cost budget and master scheduling of the aforementioned work, the proposal is basically split unit costs of items carried in fixed cost; to be considered all materials and supplies needed to complete the items, and variable costs; that will be considered labor and equipment involved in each game executed. Last Planner methodology simultaneously Sytem (Last Planner System) from the general program of work was applied, obtaining as results the Lookahead Production (Intermediate Production Planning) and Lookahead Materials (Intermediate Materials Planning), with the latter it was possible to calculate the efficiency of each item executed during the time the data were collected.
Link to repository: https://hdl.handle.net/20.500.12759/2098
Discipline: Ingeniería Civil
Grade or title grantor: Universidad Privada Antenor Orrego. Facultad de Ingeniería
Grade or title: Ingeniero Civil